Thursday, 8 September 2011

8 September 2011

1 - Discussion with Michael Thompson ref the REW.
Wall shuttering to be delivered Monday 12 - stored ready for setting up following foam glass.
Tools and compressor from Newmarket Plant Hire for Wendesday


http://www.rammed-earth.org/girtonproject.htm


2 - IR - the Slab concrete is being poured on Saturday 10 Sept - early. 5 days to set prior to ramming the Wall.
3 - IR - Foamglass 160mm thick being delivered from Belguim - base for REW - thermal barrier to hold 13 tonnes - Tuesday - fitted ready for ramming Thursday / Friday.
4 - Shuttering for the slab is being set up - (see images) - discussion with IR ref moving D1 W1 and W22 back 50mm to line with SIPS.
5 - SIPS uk sign off for all drawings - manufacture go ahead given
6 - Order placed for sliding / folding doors / Tim Bolton / ecomerchant SolarLux SL66 doors


meshwork over clay-heave panels (photo-J Lodge)
Formers and shuttering for the slab