Wednesday, 14 September 2011

10 September 2011

1 - Slab laying by DJE - Saturday 10th, 8am to 1pm (5 days to cure before ramming the earth wall) , photos below,
2 - Window chamfer detail for rooflights - SIPS uk to create chamfer as drawings sent to JL.
3 - Revision to roof light schedule
R1 = P04
R2 = C02
R3 = P04
R4 = P04
R5 = M04
R6 = P04
PDF available of revised roof light layout.
4 - KH to discuss window cills with IR and BN - window supplier
5 - IR - remove cellotex from boiler room - not needed - see spec pg37
6 - IR to extract cost for ACO drains from quotation, for adding to paving budget.
7 - SIPS uk - revised steelwork over D4 - goalpost to spread load.
8 - Water company visited - all on board - IR managing
9 - Power networks visiting Friday 16 Sept
10 - National Grid Gas to respond