Wednesday, 31 August 2011

31 August 2011

1 - Discussion with IR - Andy Watson is working on the alignment issue for the problem piles and hopes to have a solution Thursday.
2 - Eco merchant have sent drawing for D9 and D10 for approval. Fitting to be quoted by Eco Merchant.
3 - Electricity Power Networks paid to carry out survey and begin connecting.
4 - Discussion with Monika at SIPS uk - all ready, bar the re-working of the calculations to remove the vertical supports on the internal roof cut-aways (See images)




No comments:

Post a Comment