1 - IC covers replaced with cast iron as spec 3.04
2 - Car port conduit to be drilled at marked location
3 - New IC at back door -ref Ian Rudd - too many pipes for 1 IC
4 - Worked through window schedule - issue to green steps and Eco Merchant
5 - Design for D1 and D6 (email for a copy)
6 - Temporary power to IR cabin from armor cable running to Horses field.
Use for external plug when project is completed.