Thursday, 13 October 2011

13 October

1)- REW collapse Friday 30 September - since then…
2) Ground cleared and earth screened at Martin Meade's is Swaffham
3) Samples sent to Mohammed Jaffa for testing with 7% cement
4) New sample blocks made, one with 7% white and one with 7% grey
5) Shuttering repaired by MT
6) Scaffold repaired an realigned (6ft lift)
7) Project time plan adjusted by 2 week delay
8) SIPS and Regal agree to build house in 2 stages - (see below)
9) Foamglas base cleared and slab cleaned (no damage to the slab)
10) New foamglas ordered, arrived 12 Oct and fitted
11) Shuttering set to be put in place on Friday 14 Oct.
12) Newmarket plant arriving with compressor and hoist for Friday.


The plan
To build 3.2m of the wall from 17 - 21 Oct.
SIPS and Regal then arrive on Monday 24 to build the house leaving a section of roof clear above the wall (dae TBC)
We then build the remaining 2m of the wall degrading the cement as we rise to reduce colour band.(3-4 days work)
SIPS and Regal then return to finish the house, and IR continues his build program.


Wall compete - and removing shuttering - down to last low section

Wall collapsed under own weight - tall, non stabalised walls need to be built
slowly and allowed to dry as you build - oh hindsight

All the soil is shifted- with Help form Jeremy Lodge our architect.

It was beautiful though